29th October 2026
Mr Jonathan Davies
Section 151 Officer
Stockport Council
Town Hall
Stockport
SK1 3XE
emailed to – jonathan.davies@stockport.gov.uk
Thursday, 29 October 2026
Dear Mr Davies,
Vale View Primary School, Harcourt Street: unexplained funding discrepancies – request for review and response.
I am writing to you as the Council’s Section 151 Officer about unresolved discrepancies in the funding and cost of Vale View Primary School, Harcourt Street, North Reddish. I have raised these with the Council since 2008 and have never received a full explanation. All of the figures below come from the Council’s own reports.
1. Closure of the funding shortfall
The Project Highlight Report for 15 May to 27 July 2006 shows available funding of £5.80 million against a projected cost of £8.20 million, a shortfall of £2.40 million. The Highlight Report for 15 April to 15 May 2008 shows both figures as £9.94 million, so the shortfall is recorded as nil. I have not been told how the £2.4 million gap was closed. Anticipated capital receipts, including from Fir Tree Primary School, do not appear to account for it.
2. Arithmetic error in the 2008 cost report
The Council report of 22 March 2008 gives a total cost of £9,930,000. Its itemised components add up to £9,840,000, a difference of £90,000.
3. Rise in borrowing
Anticipated borrowing was £1.8 million. I understand actual borrowing reached £6.9 million. Please confirm the correct figure and explain the reasons for the increase.
4. Rising project cost
The stated cost rose from £5.5 million (October 2005) to £7.5 million (December 2005), £8 million (February 2006), £9.93 million (May 2008) and around £10 million by 2012. Some records put the final cost as high as £11 million. Please confirm the final outturn cost and its funding sources.
5. Earlier knowledge of costs
In February 2008 Cllr Weldon confirmed that costs above £5.4 million were known to the Council as early as December 2005.
6. Pre-meeting agenda of 30 March 2007
This records “obvious concern over funding” and a discussion of how much of that concern should appear in the Project Board Highlight Report.
I first raised the funding gap as a question in February 2008 and chased it through 2008 and 2009. An Information Commissioner’s Office order of 2 March 2009 required the Council to respond. I did not receive a formal answer. The only explanation I was ever given was informal.
I would be grateful if you would:
(a) Review these discrepancies and let me have a written explanation of how the £2.4 million shortfall was closed and how borrowing rose from £1.8 million to £6.9 million.
(b) Confirm the final cost of the scheme and each source of funding.
(c) Confirm whether the arithmetic error in the March 2008 report was ever identified or corrected.
(d) Confirm whether any of this evidence has been passed to you previously. I have submitted it to the Council before and I am not aware that it ever reached the Section 151 Officer. If it did, please let me know when and what, if anything, was done. If it did not, I ask that you treat this as a formal referral.
(e) Let me know whether you consider any of these matters should be reported to the Council’s external auditor, and, if not, why not.
I can supply copies of the documents referred to above on request. If any part of this should properly be treated as a request under the Freedom of Information Act 2000 or the Environmental Information Regulations 2004, please treat it as such.
I would appreciate an acknowledgement within 5 working days and a substantive reply within 20 working days.
Yours sincerely,
Sheila Oliver
Editor, The Romiley Gazette