4th November 2026

Offerton was promised a new library, sports hall and gym in return for the old Dialstone Centre. Planning papers show the homes were built. They do not show why the hub never was.

The Dialstone Centre on Lisburne Lane was once a council-run community centre with a sports hall, a smaller hall and gym, a youth centre and a library. Today its site is covered by around 94 new houses. The replacement that Offerton residents were promised, a modern community hub on nearby Blackstone Field, was never built.

The Gazette has read the planning papers that survive. They show clearly what was promised, and when the plans changed. They do not explain why.

The promise

In 2011 Stockport Council’s executive agreed to work with developer THi Riverside on three linked sites: the Dialstone Centre, Blackstone Fields and the former Dial Park school. The Council said it would use money from selling the Dialstone Centre to pay for new community facilities nearby, at no cost to the taxpayer, according to Insider Media’s report at the time.

The plans for Blackstone Field were detailed. A design statement dated 25 November 2013 describes a 1,770 square metre community hub with a library, a large multi-sports hall, a first-floor gym, changing rooms, a floodlit 3G football pitch and a grass pitch. It says the services run by Stockport Sports Trust at the old centre were “open to the public and especially popular with sports clubs”, and that the new facilities would build on them. A medical centre, pharmacy and convenience store were to sit alongside.

The applicants said that 79.3 per cent of residents who replied to their consultation backed the development overall.

What was built

The housing came first. Planning permission for the Dialstone Centre site, application DC/048027 (Bellway Homes), was granted on 25 October 2013. By 2017 a Council report described it as “nearing completion”.

The hub did not follow. A permission for Blackstone Field (DC050476) was also granted on 25 October 2013, but the Council’s own 2017 report records that it “expired unimplemented”. In December 2013 a revised application, DC/054285, dropped the nursing home and shrank the medical centre. It also added 27 social homes at the southern end of the field. Committees resolved to grant it in July 2014, subject to a legal agreement. That agreement, the 2017 report says, “remains outstanding”, so the permission never took effect.

By 2017 only the housing was going ahead. Stockport Homes and MCI Developments applied for a housing-only scheme of 27 affordable homes, application DC/063988. The report says it relied on Homes and Communities Agency grant of £525,000 plus £90,000, and that without it “the project would not be viable”. It adds that the larger Blackstone Field development “will not now be implemented”. It does not say why.

Why it matters to local people

  • Public sport and a library. The 2013 design statement itself said the old centre’s sports hall was open to the public and popular with clubs. The hub that was to replace it was dropped. The planning papers we have seen show no sports hall or gym provided in its place, only small payments towards recreation, such as £17,058 for formal recreation in the 2017 housing scheme.
  • Open space. The 2017 report says 1.6 hectares of local open space lost at the Dialstone Centre site was “yet to be replaced”, and that the former Dial Park school land would be grassed to make up for it. A Planning Inspector later upheld a Council enforcement notice against Bellway for building a large earth mound on part of the open space on the Dialstone site, in October 2018.
  • The field itself. The Council’s own report calls the wider Blackstone Field “known to be heavily contaminated, being a former landfill site”. It also notes boggy ground and a former children’s play area whose equipment had been removed. Housing went on part of the field. The playing field was lost to local people before any replacement was built.
  • Money. A Council performance report for the first quarter of 2013/14, cited by the Gazette, listed the Dialstone facility re-provision as a major scheme with £4.298 million of Council funding. We do not yet know what was spent, or what it bought.

One local resident warned at the time that the housing-only scheme looked like “cherry picking” the profitable parts of the earlier plans without the community facilities promised. The Council’s report did not answer that point.

Was it the contamination?

The cost of dealing with contamination is one candidate, but the papers do not say so. A Council reply to a 2011 information request said an executive report allowed £0.6 million for remediation on Blackstone Fields on top of normal building costs. Stockport Labour later said that THi Riverside told the Council in November 2012 that the plans were not viable, and that the Council proposed a £750,000 bailout. That is the party’s account, and we have not seen the underlying reports.

It could equally have been the developer’s finances, the cost of the care home or medical centre, or changes in NHS plans. Nobody has told residents.

What we have yet to find out

  • Who decided the hub would not proceed, when, and on what advice.
  • What the Council paid, and what it received from selling the Dialstone Centre.
  • Whether the replacement play area and Dial Park open space were ever delivered.
  • Where the library and sports clubs went.
  • Whether any sports facility has replaced it. Minutes of the Stepping Hill Area Committee on 3 December 2024 appear to record members discussing a new leisure or sports facility in Offerton as an ambition for the Council.

Separately, the Council’s 2022 budget consultation said Dialstone (Offerton) Leisure Centre had been closed since January 2022 after flood damage and proposed closing it permanently. We have not yet confirmed how that ended, or whether it is the same building.

The Gazette is asking the Council these questions under the Environmental Information Regulations (see below).

FoiA/EIR request sent to Stockport Council 4/11/2026

  1. All documents recording the decision to end, vary or not proceed with the hub on Blackstone Field: who took it, when, on what advice, and the reasons given.
  2. All documents explaining why the legal agreement (planning obligations) for application DC/054285 was never completed, the date that application was withdrawn or otherwise disposed of, and its present status on the planning register.

Paragraph 74 states “Existing open space, sports and recreational buildings and
land, including playing fields, should not be built on unless:
 an assessment has been undertaken which has clearly shown the open
space, buildings or land to be surplus to requirements
 the loss resulting from the proposed development would be replaced by
equivalent or better provision in terms of quantity and quality in a suitable
location
 the development is for alternative sports and recreational provision, the needs
for which clearly outweigh the loss.”

In respect of plan no 48028 for the proposed redevelopment of part of Blackstone Field for a new community hub incorporating a four court sports hall, gym, changing rooms, viewing area, one floodlit all weather five-a-side football pitch, one seven-a-side grassed football pitch, multi-function community room and library, medical centre, pharmacy, small retail unit (200m2 net).

https://sportengland-production-files.s3.eu-west-2.amazonaws.com/s3fs-public/sport-england-model-planning-conditions-december-2012.pdf

https://consultation.stockport.gov.uk/policy-performance-and-reform/service-review-leisure-budget-consultation-phase-2