29th August 2026

Key facts from the documents

  • Site area: approximately 1.8 hectares.
  • Primary technique actually used: engineered clean cover system (minimum 400 mm of validated topsoil/subsoil + geotextile/capillary break) across soft landscaping and sports pitch areas, plus localised asbestos hand-picking/removal and gas-protection membranes in the buildings.
  • Full deep excavation and off-site disposal of the entire made ground (up to 7 m thick in places) was not carried out.
  • The £9.94 million figure noted by the Executive in March 2008 was before the full contamination was publicly admitted and the main remediation works were finalised.

Cost estimate

ElementEstimated cost range (2010–2011 prices)Notes
Engineered cover system (≈1.0–1.3 ha of soft areas)£250,000 – £550,000400–500 mm clean imported material + geotextile. Typical cover-system rates at the time were roughly £20–£45/m².
Localised asbestos management & hand-picking£80,000 – £250,000Highly variable; depends on volume of affected material. Hand-picking and licensed disposal of asbestos-contaminated soils is expensive.
Gas-protection measures in buildings£40,000 – £100,000High-spec DPM + detailing on concrete slabs.
Validation testing, supervision & verification reporting£40,000 – £80,000Required for regulatory sign-off.
Contingency / unforeseen hotspots£50,000 – £150,000Common on former tips.
Total estimated remediation cost£460,000 – £1.13 millionMost likely mid-range: £650,000 – £900,000

How this sits with the overall project cost

  • Early scheme estimates: ~£5.5 million.
  • March 2008 Executive figure: £9.94 million (already a major increase, largely from design, CPO, inflation, Sport England requirements, etc.).
  • Final out-turn was higher still once the cover system, asbestos works and delays were added.

A remediation bill in the £0.65–0.9 million range (at 2010/11 prices) is consistent with:

  • The chosen “cover and contain” strategy rather than full dig-and-dump.
  • The site size (1.8 ha).
  • Contemporary UK benchmark rates for cover systems on high-sensitivity (school) end-uses.
  • The fact that the big jump to £9.94 million occurred before the main contamination works were fully scoped and executed.

If the Council had chosen widespread excavation and off-site disposal of the made ground, the remediation cost would have been several times higher (potentially £2–4 million+), but that is not what the verification reports show was done.

Note: These are reasoned estimates based on the documented technique, site area, and typical 2009–2011 UK rates. Exact figures would only be available from the final account / BAM Construction records or Stockport Council’s project file.