Why Have a Scrutiny Committee at All?” Questions Raised Over Vale View School and Stockport Council.

Vale View Primary School, Vexatious Posted on Mon, August 31, 2026 16:38

31st August 2026

A long-running dispute over the cost and capacity of a Stockport primary school has raised fresh questions about the council’s scrutiny process — and why concerns about soaring costs were dismissed as “vexatious”.

Questions are being raised over the effectiveness of Stockport Council’s scrutiny arrangements after recommendations concerning the controversial Vale View Primary School project were allegedly ignored.

The school, built in Reddish North, was originally expected to cost around £5.5 million. Project documentation subsequently showed the estimated cost rising to approximately £9.9 million.

Now, more than a decade later, the controversy has returned to the spotlight, with claims that concerns raised about the escalating costs were not properly addressed and that the person pursuing them was quickly described by the council as “vexatious”.

The dispute raises a fundamental question about local democracy:

If a council’s scrutiny committee makes recommendations, what happens when those recommendations are not acted upon?

From £5.5m to almost £10m

The financial figures are at the heart of the controversy.

Contemporary council documentation reportedly recorded the project moving from an estimated cost of around £5.5m to £9.9m.

That is an increase of roughly 80 per cent.

The increase is particularly striking because, according to the material published alongside the allegations, the movement from the lower to the higher figure appears within just two pages of a project report.

The person raising the concerns argues that the rapid increase should have prompted much closer monitoring of the project.

Instead, she says, when she questioned the figures she was branded “vexatious”.

A letter dated 5 October 2012, from Stockport Council’s then Head of Legal Services, Barry Khan, reportedly described her continuing pursuit of the matter in those terms.

The allegation that this amounted to an attempt to shut down legitimate scrutiny is strongly contested territory.

Calling someone “vexatious” does not establish that a council was attempting to conceal wrongdoing. Nor does a rapidly rising construction estimate, by itself, establish corruption.

But it does raise an important question:

Were the concerns properly investigated before the label was applied?

A school that was never big enough?

The financial questions are accompanied by a second concern: whether the new school was appropriately sized in the first place.

The investigation argues that Vale View was effectively undersized from the outset, with a permanent capacity of around 525 pupils, despite projections indicating demand could exceed that figure.

Temporary accommodation was therefore contemplated.

The school has subsequently become the subject of further questions about capacity and the apparent need to bring back into use an older school building nearby.

That raises an uncomfortable issue about the original decision-making.

If the council knew that demand could exceed the capacity of the proposed new building, why was a larger permanent school not considered?

And if three existing schools were already available, why was the alternative of renovating and upgrading those buildings not pursued instead?

Those questions go beyond the eventual construction bill.

They concern whether the fundamental investment decision represented good value in the first place.

What was the scrutiny committee for?

Perhaps the most serious allegation concerns the council’s scrutiny process.

Scrutiny committees exist precisely because councils need mechanisms through which major decisions can be examined, challenged and reviewed.

They are intended to provide a degree of democratic accountability beyond the executive decision-making process.

If recommendations made by a scrutiny committee were subsequently ignored, the public is entitled to ask why.

What did the committee recommend?

Who was responsible for responding?

Were the recommendations formally accepted or rejected?

If they were rejected, what reasons were given?

And was there any mechanism for ensuring that the committee’s concerns were not simply left on a shelf?

A scrutiny committee without an effective response mechanism risks becoming little more than a talking shop.

That is the broader democratic issue raised by the Vale View affair.

The question of “vexatious”

The most troubling element of the story, for critics of the council, is the treatment of the person who continued asking questions.

In October 2012, Barry Khan, then Head of Legal Services, reportedly wrote to her again describing her pursuit of the issue as “vexatious”.

The criticism is particularly striking given that the questions concerned public expenditure on a major council-funded construction project.

Citizens asking how millions of pounds of public money were spent should not automatically be regarded as troublesome simply because they continue asking questions.

On the other hand, councils do have legitimate grounds for managing persistent or repetitive correspondence where requests become unreasonable or disproportionate.

The crucial issue is therefore not simply whether the word “vexatious” was used.

It is whether the designation was reasonable, proportionate and properly supported by the circumstances.

Corruption or incompetence?

That leaves perhaps the most provocative question surrounding the project.

Was something more serious going on?

The accusation of corruption is a serious one and cannot responsibly be made without evidence.

But the alternative explanation — serious incompetence — is hardly reassuring if public money is involved.

A project which rises from £5.5m to almost £10m requires explanation.

A school which may not have been large enough to meet projected demand requires explanation.

A decision to build a new school rather than renovate existing facilities requires explanation.

And a scrutiny process which allegedly produces recommendations that are subsequently ignored requires explanation.

None of those facts, individually, proves corruption.

Together, however, they demonstrate why the project deserves a transparent historical examination.

The money trail

There is another reason why the story has refused to disappear.

Earlier investigation has identified a £2.243m transfer of Targeted Capital Funding associated with the Reddish North scheme which was subsequently used on four other school projects.

The council has reportedly said the transfer was authorised under Department for Education and Skills arrangements.

Again, that does not demonstrate wrongdoing.

But it does reinforce the need for a complete financial reconstruction.

Where did the original funding come from?

Why was money transferred elsewhere?

How was the resulting funding gap closed?

Why did the project’s estimated cost rise so sharply?

How much was spent on contamination and remediation?

What did drainage ultimately cost?

What was the final outturn figure?

And who signed off the various increases?

Those are precisely the questions a properly documented public-sector project should be capable of answering.

The £10m question

There is a temptation in controversies like this to reduce everything to a single accusation.

But the more important story may be the cumulative failure to provide a clear public explanation.

The issue is not simply whether Vale View Primary School cost more than originally anticipated.

It is whether the council can demonstrate that:

  • the original business case was sound;
  • alternatives were properly considered;
  • projected demand was accurately assessed;
  • escalating costs were effectively controlled;
  • additional funding was properly authorised;
  • abnormal ground and drainage costs were properly accounted for;
  • scrutiny recommendations were properly considered;
  • and residents’ subsequent questions were dealt with fairly.

If the answer to all of those questions is yes, the council should be able to demonstrate it through the documentary record.

If some answers are no, the public deserves to know why.

Why this matters today

The Vale View controversy is now more than a decade old.

But the questions have not necessarily become less relevant.

Councils continue to spend millions of pounds on schools, roads, regeneration schemes and other capital projects.

The lesson from Vale View should therefore not simply be about one school in Reddish.

It should be about how local government monitors major projects, how it responds when costs rise dramatically, and whether ordinary residents can challenge decisions without being dismissed.

Scrutiny is supposed to provide the checks and balances.

Freedom of Information is supposed to provide transparency.

And elected representatives are supposed to provide democratic accountability.

If recommendations can simply be ignored and persistent questioning can result in a resident being labelled “vexatious”, then the public is entitled to ask what those safeguards are actually worth.

The allegations surrounding Vale View do not, on the evidence currently available, prove corruption.

But they do establish a case for asking difficult questions.

And perhaps the most important one is the simplest:

If a scrutiny committee cannot ensure that its recommendations are properly considered, why have a scrutiny committee at all?



How a £5.5m School Became a £11m Question.

Vale View Primary School, Vexatious Posted on Mon, August 31, 2026 15:39

31st August 2026

Vale View Primary School was hailed as a major investment in Reddish North. But documents uncovered during a long-running investigation raise questions over soaring costs, diverted funding, contaminated land, drainage problems and the loss of public open space.

It was supposed to be a major investment in the future of Reddish North.

Instead, the story of Vale View Primary School has become a trail of rising costs, changing funding arrangements and unanswered questions.

The new school, built on the former Harcourt Street site, was initially expected to cost around £5.5 million.

Within a few years, the projected bill had risen to almost £10 million.

And documents now emerging from a long-running investigation raise questions about how that increase happened, where the money came from and whether the problems encountered during the project were properly anticipated.

There is no evidence from the documents considered so far that the council acted improperly.

But there is enough evidence to ask some uncomfortable questions.

From £5.5m to £9.94m

The financial story is difficult to ignore.

The original project estimate was around £5.5m. Subsequent estimates rose to approximately £7.5m and then £8.2m.

By 2007, the projected cost was around £8.5m.

By 2008, project documentation recorded a projected cost of £9.94m.

That represents an increase of roughly 81 per cent on the original £5.5m figure.

Later references have put the eventual cost at around £11m, although establishing the precise final outturn remains one of the key questions still outstanding.

Of course, construction projects change. Prices rise. Specifications evolve. Unexpected problems are discovered.

And Vale View was not being built on an ordinary greenfield site.

But that makes the detail of the expenditure more important, not less.

How much of the increase was inflation?

How much resulted from changes to the design?

How much was caused by contamination?

How much went on drainage, professional fees, land and other costs?

And what was the final bill?

Those questions can only really be answered by a complete project cost reconciliation.

The £2.4m hole

Perhaps the most revealing document comes from 2006.

A project Highlight Report reportedly showed the scheme with projected expenditure of £8.2m, but only £5.8m of available funding.

There was therefore a funding gap of £2.4m.

Two years later, that gap had disappeared.

But it had not disappeared because the projected cost had fallen.

The 2008 figures reportedly showed available funding of £9.94m, matching the projected expenditure.

That means the funding position had increased by more than £4m while the estimated cost had also risen.

Where did that additional funding come from?

And what approvals were required?

Those are questions about public accounting rather than accusations of wrongdoing. But they deserve clear answers.

£2.2m moved elsewhere

There is another striking part of the financial trail.

An FOI response cited during the investigation states that £2.243m of Targeted Capital Funding associated with the Reddish North scheme was used on four other projects.

More than £1m went to Brindale PRU.

A further £662,000 went to Dial Park Primary, £321,000 to Bradshaw Hall Primary and £240,000 to Woodley Primary.

The total was £2.243m.

The council reportedly explained that the transfer was permitted by a Department for Education and Skills letter dated December 2004.

If that is correct, the transfer itself may have been entirely authorised.

But another question immediately follows:

If £2.243m originally associated with Reddish North was spent elsewhere, how was the increasingly expensive Vale View project subsequently funded?

The answer should be visible in the capital programme and final accounts.

That is why obtaining the underlying departmental approval and following the money through the subsequent accounts is so important.

The site nobody could pretend was straightforward

There is a strong argument that the school became more expensive because the site itself presented significant problems.

The Harcourt Street land had an industrial history.

Investigations identified contaminants including arsenic, lead and asbestos.

The remediation strategy involved clean cover, localised asbestos removal and protection against ground gases.

Contaminated land can be extremely expensive to deal with, and contemporary project documents apparently recognised that the final extent of remediation work was uncertain.

That may provide a perfectly legitimate explanation for some of the additional expenditure.

But it also creates an obvious test for the project’s finances.

If the original £5.5m estimate assumed relatively normal construction conditions, the final accounts should make it possible to identify precisely how much was subsequently spent dealing with abnormal ground conditions.

Without that breakdown, the public is left comparing two headline figures without knowing what lies between them.

A £200,000 drainage warning

Then there was drainage.

Before construction, project documentation reportedly identified a high risk that Environment Agency requirements could push drainage costs beyond a provisional allowance of £200,000.

After the school opened, problems were reported with standing water and drainage around the site, including concerns relating to nearby Jackson’s Pond.

That creates another potentially important before-and-after story.

A risk was identified.

Money was provisionally allowed for it.

Problems were subsequently reported.

So what happened?

Was the eventual drainage system different from that originally envisaged?

How much did it cost?

Were additional works required?

And did the completed system resolve the problems?

These are not allegations. They are questions which should be answerable from the project’s records.

What happened to the playing fields?

The financial story is only part of the investigation.

The development also changed the nature of the land itself.

The former site provided a significant area of open recreational space. Attention has now been drawn to a 1982 Section 52 agreement, apparently requiring around seven acres of recreational open space.

The new development introduced the school buildings, playgrounds, hardstanding and fenced sports facilities.

The question is whether the public lost open recreational land and, if so, whether the replacement arrangements provided an equivalent benefit.

That is particularly relevant because the planning process also involved commitments relating to sports provision and community access.

The Sport England question

Sport England’s involvement provides another piece of the puzzle.

The investigation has identified commitments made in connection with the development which were intended to address concerns about sports provision.

The question now being pursued is whether those commitments were fully delivered and whether the facilities subsequently provided the community access that had been envisaged.

That may sound like a technical planning matter.

It isn’t.

When public recreational land is lost to development, the promises made to secure planning approval matter.

So does what happens to those promises years later.

A school too small for the children who needed it?

There are also questions about capacity.

Contemporary projections reportedly suggested that demand could reach between 555 and 563 pupils.

Yet the permanent school was designed around a capacity of 525.

Temporary accommodation was proposed to deal with the difference.

That raises an uncomfortable question about whether the new building was adequately planned for the population it was intended to serve.

A school can be expensive to build.

It is more difficult to explain why a new school should require temporary accommodation if demand above its permanent capacity was already foreseeable.

And then there was the traffic

Residents also raised concerns about access and traffic, particularly around narrow Mill Lane.

After the school opened, traffic-management and road-safety problems reportedly emerged, with police concerns also recorded.

Again, the issue is not whether someone could have predicted every problem.

It is whether the risks identified during planning were properly assessed and whether the completed scheme delivered the safe and practical access that residents had been promised.

The missing document

Perhaps the most significant feature of the entire story is what is still missing.

There is no shortage of figures.

There are estimates.

There are project reports.

There are funding allocations.

There are risk registers.

There are FOI responses.

There are references to contamination, drainage, sports facilities and open space.

But what is still needed is the document that brings everything together:

the final, fully reconciled cost of Vale View Primary School.

That document should show how the project moved from its original estimate to its final cost.

It should identify approved variations.

It should separate construction inflation from changes in scope.

It should identify abnormal ground costs.

It should account for professional fees, land, drainage, remediation, contingencies and other expenditure.

And it should explain how the funding package changed as the estimated cost increased.

The bigger question

The story of Vale View Primary School is not necessarily a story of corruption or financial wrongdoing.

The evidence examined so far does not establish that.

It is, however, a story about public money and public decisions.

A project that began at around £5.5m ended up with a projected cost approaching £11m, while millions of pounds of capital funding moved between projects and significant risks emerged from the site’s contamination and drainage requirements.

The school was built.

Children attend it.

The investment undoubtedly delivered a new educational facility for the area.

But that does not mean the questions should disappear.

Public confidence depends not only on whether a project is completed, but on whether the public can subsequently understand what it cost, why it cost that much and whether the decisions made along the way represented good value.

For Vale View, the paper trail appears to contain many of the pieces.

The outstanding challenge is to put them all together.

And until the final numbers are reconciled, one question remains hanging over the project:

How did a £5.5m school become a £10m-plus project — and where, exactly, did all the money go?



How a £2.4 million school funding gap quietly disappeared.

Vale View Primary School, Vexatious Posted on Mon, August 31, 2026 15:15

31st August 2026

Internal reports show Stockport Council closed a major shortfall on the North Reddish primary school by increasing the available budget rather than cutting costs

Internal project reports obtained by this newspaper reveal how a £2.4 million funding shortfall on Stockport’s planned new primary school in North Reddish was eliminated between 2006 and 2008 — not by reducing the cost of the scheme, but by substantially increasing the money made available for it.

A Highlight Report covering the period 15 May to 27 July 2006 recorded available funding of £5.80 million against a projected overall cost of £8.20 million for the 2.5-form-entry school plus children’s centre. The variance — a shortfall of £2.40 million — was clearly flagged.

By the time of the next available Highlight Report, covering 15 April to 15 May 2008, the picture had changed completely. Available funding had risen to £9.94 million and the projected overall cost stood at exactly the same figure. The variance was recorded as zero.

The documents show that the projected cost of the scheme continued to climb. Early estimates had been in the region of £5.5 million. By mid-2006 the figure had reached £8.2 million. By spring 2008 it stood at £9.94 million — the sum formally noted by the Council’s Executive when it approved the Compulsory Purchase Order for the Harcourt Street site.

What closed the gap was not a reduction in projected spending. Instead the “available funding” line was increased by more than £4 million so that it matched the higher estimated cost.

The reports form part of the internal monitoring of the project that eventually became Vale View Primary School. They sit alongside other contemporary documents that recorded “obvious concern over funding” in 2007 and a high risk that Environment Agency drainage requirements would exceed the provisional sum set aside for them.

The final cost of the completed school, and a full breakdown of how the additional funding was sourced, have never been published in detail.



The £11m school that began at £5.5m: where did the money go?

Vale View Primary School, Vexatious Posted on Mon, August 31, 2026 14:21

31st August 2026

Documents reveal a decade-old financial mystery surrounding Stockport’s proposed North Reddish school

A proposed new primary school in Stockport that was originally expected to cost around £5.5 million eventually reached an estimated £11 million, while millions of pounds of funding were being moved around the Council’s school-building programme.

Now a collection of contemporaneous Council documents and correspondence raises questions about how the project’s finances were managed — and why repeated requests for an explanation were not answered.

The proposed school was planned for the Harcourt Street playing-field site in North Reddish, despite concerns about contamination at the site.

Documents show the estimated cost escalating rapidly. Within months, figures of approximately £7.5 million, then £8.2 million, and ultimately around £10 million appeared in the project’s financial history before contamination remediation costs were added.

Yet the financial questions were being raised while the project was still developing.

In August 2007, campaigner Sheila Oliver wrote directly to then Council Leader Councillor Dave Goddard after spotting what she regarded as a discrepancy in a Council planning document.

She quoted a Council document saying that the proposed sale of the Fir Tree site would provide 20 per cent of the cost of the new school, then stated that she understood the sale would raise only about £1.2 million, with a further £600,000 associated with Sport England requirements.

Her question was blunt:

How could the Fir Tree sale represent 20 per cent of an £8.5 million school?

The significance of that question becomes clearer when another Council response is examined.

In August 2007, Stockport Council responded to an FOI request concerning the proposed North Reddish school and school-site sales.

The response stated that the Targeted Capital Fund funding allocated to the Reddish North Primary School scheme had been used to finance projects at four other schools.

The amounts listed were:

  • Brindale Pupil Referral Unit — £1.020 million
  • Bradshaw Hall Primary School — £321,000
  • Dial Park Primary School — £662,000
  • Woodley Primary School — £240,000

Total:

£2.243 million

The Council said this had been done in accordance with permission contained in a Department for Education and Skills letter of 15 December 2004.

That raises an obvious question:

Why was £2.243 million originally allocated to the Reddish North scheme being used to finance other school projects, and how was the Reddish North scheme subsequently financed?

The answer may lie in the Council’s capital accounts and committee papers — but those records have yet to be assembled.

There is another remarkable document.

In November 2006, project manager Donna Sager wrote to Ms Oliver assuring her that there was no problem with the project’s funding.

But correspondence from around the same period records a £2.4 million shortfall on a project that had only recently been expected to cost £5.5 million.

The estimated cost subsequently continued to rise.

By the time the estimate reached approximately £10 million, the financial position had become dramatically different from that originally presented.

And there was another complication: the land on which the school was proposed was subsequently acknowledged to have significant contamination issues.

The Council’s own correspondence from 2007 shows that contamination was already having financial implications.

A ground investigation report discussed excavation and possible removal of contaminated material, with an allowance of £38,800 included in the cost plan for additional work in one area.

A further £82,350 was allowed for installation of a gas membrane.

The correspondence also acknowledged that the extent of excavation and removal had not yet been fully established and that the costs would develop as the work progressed.

At the same time, questions were being raised about whether the investigation had adequately established the condition of the whole site.

The proposed development therefore faced two moving targets: the cost was escalating, while the extent and treatment of contamination were still being worked out.

Yet the crucial question remains unanswered:

What did the project actually cost in the end?

Ms Oliver says she repeatedly tried to establish the answer.

In a letter to Councillor Goddard she stated that she had been drawing the Council’s attention to financial irregularities for many months, had supplied evidence, had raised questions in Council meetings and had made formal complaints.

The Council Leader’s response, dated 3 September 2009, is revealing.

Following a public question at the Council’s Executive Meeting on 1 September, Ms Oliver had asked:

“For the past 18 months or so I have tried very hard to draw the Council’s attention to financial anomalies of several millions of pounds without success.”

Councillor Goddard replied that he was unable to answer because, he said, the question did not provide details of the alleged anomalies and Ms Oliver was unwilling to identify them.

That response is difficult to reconcile, at least on its face, with the documentary correspondence already available.

Concerns about the cost were raised while the project was still live. In a letter to senior Stockport councillors and officers dated 15 September 2007, campaigner Sheila Oliver challenged the Council’s projected £8.5 million cost for the proposed Harcourt Street school. She set out her calculations comparing the proposed cost with government new-build figures and the Council’s own asset valuations, concluding that “something does not add up regarding the cost” and asking for a full explanation. This followed an earlier letter in August in which she had questioned the Council’s claim that the sale of the alternative Fir Tree site would provide 20% of the school’s cost. These documents are significant because they show that concerns about both the escalating cost and the proposed funding arrangements were being put directly to the Council at the time, rather than being raised only retrospectively. They also raise a straightforward question: if senior councillors and officers were being warned in 2007 that the project’s cost and funding did not appear to add up, what investigation was undertaken, and where is the resulting explanation?

Two years earlier, on 27 August 2007, Ms Oliver had put a specific funding question to the Council Leader concerning the Fir Tree site and the £8.5 million school cost.

The Council’s own FOI response of the same period also records the £2.243 million reallocation of funding originally allocated to the Reddish North scheme.

The documents therefore leave several questions hanging.

What was the original approved budget?

Why did the estimated cost rise from £5.5 million to approximately £11 million?

What was the final outturn cost?

How much additional money was ultimately required?

What happened to the £2.243 million of Targeted Capital Fund money allocated to Reddish North?

What did the Fir Tree land actually realise, and how was that receipt accounted for?

Did contamination contribute materially to the eventual cost?

And why was the alternative Fir Tree site not used for the new school?

None of these questions, by themselves, establishes fraud.

Nor does the existence of a large cost increase prove financial misconduct. Major public construction projects can experience substantial increases for entirely legitimate reasons.

But that is precisely why the questions deserve answers.

If there was a straightforward explanation for the movement of the money, the Council’s accounts and capital-programme records should, in principle, provide it.

And if the final cost was substantially different from the figures being presented during the project, taxpayers have a legitimate interest in knowing why.

There is an additional historical irony.

The Council Leader’s letter of September 2009 carried a footer stating that Stockport was “officially one of the best councils in Britain, according to the Audit Commission March 2009.”

For the campaigner who had spent years asking where millions of pounds had gone, that endorsement must have made the unanswered questions all the more striking.

The mystery is not whether the figures changed.

The documents show that they did.

The mystery is how the project got from £5.5 million to around £11 million, how the funding was rearranged along the way, what the final bill was — and why a citizen repeatedly asking for the figures was unable to obtain a satisfactory answer.



Removing Public Open Space.

Vale View Primary School Posted on Mon, August 31, 2026 13:54

31st August 2026

1. Is the open space required by the 1982 S.52 Agreement still there now that the school has been built?

From the available evidence (the 2009 Weldon letter, the site plans, aerial imagery, and the school layout):

  • Cllr Weldon’s letter of 6 April 2009 stated the Council’s position that none of the seven acres of open space required under the 1982 S.52 Agreement was included in the Compulsory Purchase Order and that the school would not be built on that protected land.
  • The school (Vale View) and its associated hardstanding, buildings, playgrounds and fenced sports pitch occupy a substantial portion of the former open playing-field / tip site.
  • A fenced school football pitch with “managed public access” was provided as part of the scheme (visible on the site layout plan). This is school land, not unrestricted public open space.
  • Surrounding residual green areas exist on the periphery, but they are significantly smaller than the original open field and are not the seven acres of dedicated public recreation land that the 1982 agreement required to be set aside.

Conclusion
The large, freely accessible open space that previously existed on the Harcourt Street / Mill Lane field has been largely replaced by the school buildings, hard surfaces, playgrounds and a managed school pitch. Whether any remaining peripheral land exactly matches the (vaguely defined) seven acres protected by the 1982 S.52 Agreement cannot be confirmed from the public documents alone, but the overall quantum and character of public open space on the site has been substantially reduced.

2. Could the site accommodate the Sport England demanded facilities?

Sport England’s requirements for a new primary school of this size typically include:

  • A full-size or near full-size grass pitch (or equivalent artificial surface) meeting minimum dimensions and runoff areas.
  • Adequate soft outdoor PE space.
  • Protection of playing-field quality and quantity (they strongly resist net loss of playing-field land).

From the site layout plan and the 1.8–2.97 ha overall site area:

  • A fenced school football pitch was provided.
  • Additional playgrounds for different age groups and a netball court were also included.
  • However, the usable grass pitch area is constrained by the school buildings, parking, access roads and the need for the clean cover system over the contaminated made ground.
  • The pitch is described as having “managed public access,” which is a compromise rather than the fully public open recreation space that previously existed.

Conclusion
The site was able to accommodate a school pitch and outdoor PE facilities that met the minimum requirements Sport England would have insisted on for planning approval. It did not, however, retain the previous large, unrestricted public playing field. The facilities provided are school-oriented and more limited in area and public accessibility than the original open space.



Harcourt Street – Let’s Forensically Look At What Went On.

Vale View Primary School Posted on Mon, August 31, 2026 13:51

29th August 2026

Thank you for getting in touch with the Department for Education.


We received your Freedom of Information request today and our aim is to respond within 20 working days, as set out in the Freedom of Information Act 2000.


The reference number we have given your request is: 2026-0086605 
 

You requested:

Freedom of Information request – DfES permission dated 15 December 2004 concerning the Reddish North allocation

I am requesting copies of information held by the Department for Education (DfE), including records of its predecessor, the Department for Education and Skills (DfES), concerning a permission, approval, consent, authorisation or similar decision dated 15 December 2004 relating to Stockport Metropolitan Borough Council and the Reddish North allocation.

I understand that a DfES permission dated 15 December 2004 is referred to in connection with this matter. I am seeking the actual document and the records surrounding it, in order to establish precisely what the Council was permitted to do with the Reddish North allocation and what conditions, restrictions or requirements applied.

Please provide:

A copy of the DfES permission, approval, consent or authorisation dated 15 December 2004 relating to the Reddish North allocation and/or Stockport Metropolitan Borough Council.
Any letter, submission, application, briefing, recommendation or other document submitted to DfES which preceded or accompanied the granting of that permission.
Any correspondence between DfES and Stockport Metropolitan Borough Council concerning the request for, consideration of, or granting of the permission.
Any documents which explain the legal, statutory or policy basis on which DfES granted the permission.
Any conditions, restrictions, qualifications or requirements attached to the permission, including anything concerning the purposes for which the Reddish North allocation could be used.
Any subsequent correspondence or records held by DfE/DfES concerning the interpretation, implementation, compliance with, or variation of the 15 December 2004 permission.
Any file reference, case reference, project reference or other identifying information associated with these records.

For clarity, I am particularly seeking to establish:

what Stockport Metropolitan Borough Council asked DfES for permission to do;
what DfES actually authorised on 15 December 2004;
whether the authorisation applied specifically to the Reddish North allocation;
whether the authorisation was subject to any conditions; and
whether the Council subsequently sought or obtained any further approval or variation.

If the relevant records are not indexed under the expression “Reddish North allocation”, please search for the underlying matter using the names Stockport Metropolitan Borough Council, Reddish North, and the date 15 December 2004, together with records relating to any application for or grant of approval/permission concerning the allocation.

If the records are held by a predecessor department, transferred to another government body, or deposited with The National Archives or another archive, please identify the body or collection now holding them and, where possible, provide the relevant reference.

If any part of the requested information is exempt from disclosure, please provide all non-exempt information and identify the exemption relied upon for each withheld part.

I would prefer the information to be supplied electronically, preferably as PDF copies of the original documents where available.


Answers to a wide range of education related questions can be found online at: Department for Education – GOV.UK (www.gov.uk)


You can also contact our general helpline on 0370 000 2288. Lines are open Monday to Friday, from 9.30am to 5pm.

Department for Education



FOIA Request About Sport England Public Facilities At The Vale View School.

Vale View Primary School Posted on Mon, August 31, 2026 13:47

31st August 2026

Subject: Freedom of Information Request – Sports provision at Vale View Primary School / Harcourt Street, Stockport

To: Subject: Freedom of Information Request – Public Sports provision at Vale View Primary School / Harcourt Street, Stockport.

Dear FOI Team,

To: foi@dcms.gov.uk

I am making this request under the Freedom of Information Act 2000.

In January 2016, DCMS wrote to me stating that sports provision had been delivered at the former Harcourt Street site (now Vale View Primary School, North Reddish, Stockport) and had been made available for community use. This followed Sport England’s 2007 decision to withdraw its objection to Stockport Council’s planning application on playing-field-loss grounds, after the council proposed on-site sports provision at Harcourt Street and offsite improvements at Fir Tree Primary School.

I would be grateful if you could provide:

  1. All correspondence, briefings, or internal records between DCMS and Stockport Metropolitan Borough Council (or Sport England) between 2013 and 2016 concerning sports provision at the Harcourt Street/Vale View site, including any evidence submitted to support the claim that provision had been “delivered and made available for community use.”
  2. The name/job title of the official(s) who drafted or approved the January 2016 letter sent to me on this matter, and any internal sign-off record for it.
  3. Any evidence held by DCMS confirming that on-site sports facilities at Harcourt Street were, at any point, actually accessible to the public or the wider community (as opposed to school use only).
  4. Any records held regarding the offsite sports improvements proposed at Fir Tree Primary School, and any communications noting or considering the closure and disposal of the Fir Tree site in 2011.
  5. Any records of correspondence between DCMS/Sport England and Stockport Council reviewing or auditing whether the sports provision commitments used to secure Sport England’s withdrawal of objection were actually fulfilled.

If any of this information is held by Sport England rather than DCMS, please confirm this and, if possible, transfer the request under section 1(1) of the Act, or advise me so I can submit directly.

Please provide the information in electronic format. If any part of this request is refused, please specify the exemption relied upon and provide details of your internal review and ICO complaint procedures.

Yours faithfully,
Sheila Oliver



School Built On Toxic Tip Was Plagued By Flooding As Council Still Blocks Questions, As With Padden Brook.

Vale View Primary School, Vexatious Posted on Mon, August 31, 2026 07:23

31st August 2026

When Stockport Council chose the former Jackson’s Brickyard site in North Reddish for a new primary school, it knew the land was an infilled clay pit. Early cost estimates sat around £5.5 million. By September 2007 the figure had risen to £8.5 million, of which a provisional £200,000 was allocated for drainage. Internal project risk registers compiled two months later rated the chance that the Environment Agency would require additional drainage works — and extra cost — as high.

The school, later named Vale View Primary, eventually opened in 2011 after further delays, a revised scheme cost of £9.94 million noted by the Executive in 2008, and a remediation strategy based largely on an engineered clean cover system rather than full removal of contaminated material. Arsenic, lead and asbestos had been confirmed on the site. Children were photographed sitting on the grass during a ceremonial turf-cutting before full remediation was complete.

Drainage, however, remained an unresolved problem. Photographs taken years after opening show large areas of standing water on the school playing fields and adjacent grass. The site sits above an aquifer that drains towards Jackson’s Pond, the home water of Reddish Angling Club.

In June 2015 the Manchester Evening News reported that the angling club had threatened to take Stockport Council to court. The club said it had agreed in writing to allow the pond to serve as an overflow for excess water from the school fields, on condition that proper drainage was installed. According to club officials, the pipe that was provided was only half the agreed size and frequently blocked. The pond flooded repeatedly after 2011. Members spent more than £8,000 of their own funds raising the banking by 18 inches and on at least one occasion called the fire service to pump water away. Long periods followed when the pond was unusable. The Council acknowledged the difficulties, said roots had been cleared from the pipe, but accepted that the problem had not been solved.

Despite the clear documentary trail — the provisional sum, the high risk rating in 2007, the post-opening waterlogging and the angling club’s public dispute — attempts to obtain a final account of how much was actually spent on drainage, and whether the system performed as designed, have been frustrated for years. Freedom of Information and Environmental Information requests on the subject have been refused, delayed or blocked.

Monitoring Officer Vicki Bates is reported to regard continued questions about the drainage at the Harcourt Street / Vale View site as vexatious, in the same manner in which she has treated persistent inquiries about drainage problems at Padden Brook. Campaigners argue that applying the “vexatious” label to long-standing, evidence-based concerns has the practical effect of closing down legitimate public scrutiny of spending and environmental performance on a contaminated former tip that drains into a local fishing pond.

Stockport Council and the Monitoring Officer were approached for comment.